Soule : P-13528

« Go Back
Loading...

Summary

  • P-13528
  • Soule River
  • Alaska
  • AK
  • 77.00 MW
  • Proposed
  • Conventional

Permit

  • Download Permit
  • 05-20-2013
  • 04-30-2016
  • Soule Hydro, LLC (APT)

Description

After the first perliminary permit expired, Soule Hydro filed a succesive perliminary permit application on Sept 1, 2012 which FERC approved on may 20, 2013.

Soule Hydro has proposed a highter dam (265-foot-high, 903-foot-long) in  its second application and proposed an installed capacity of 77 MW.

In a progress report filed in February 2013, APT stated that it is making progress on the project and is seeking Presidential Permit from the State Department to connect the project with powe grid in British Columbia.

Proposed Project Structures:

  • 160-foot-high, 1000-foot- long concrete dam;
  • 12,000 foot-long tunnel;
  • 9.7 mile-long 138 kV transmission;
  • 2.6-mile-long road.

 

 

About Alaska Map

This interactive website is supported through a partnership between the Hydropower Reform Coalition and the National Park Service.  Its purpose is to allow stakeholders to share information about important resources, including recreation, in the vicinity of proposed hydropower projects in Alaska.  HRC and NPS will use this input to set priorities for our involvement.

We encourage you to share any resource related information you may have about the proposed project area through our contact us page.   Please be aware that this website is not a substitute for FERC’s e-Comment system.  If you wish to have your comments considered by FERC and the project applicant, please see these instructions on how to e-Comment.