On April 17, 2008 FERC issued a license that will allow Priest Rapids project on Columbia River to operate until 2048 AD.
FERC issues a 40-year license for Priest Rapids project on mid-Columbia River
Project:
Priest Rapids : P-2114
On April 17, 2008 FERC issued a license that will allow Priest Rapids project on Columbia River to operate until 2048 AD. ![]() FERC rejects application for hydropower on McKenzie River
By: Rupak Thapaliya Thursday February 14, 2008
FERC has rejected a preliminay permit application filed by Principle Power Hydro for hydropower production from McKenzie River in Lane county, Oregon. ![]() FERC continues with inadequate carbon analysisIn a recent Environmental Assessment (EA) of Morgan Falls project, FERC has yet again failed to perform a complete analysis of carbon footprint of the project. ![]() FERC's final rule amending CEII regulationsA little more than four years after they were first issued, FERC has amended its CEII regulations. The amended regulations (read FERC's final rule or its order on rehearing) have several significant new features. ![]() Preliminary Permit application filed for Newport Wave Park Project
By: John Seebach Thursday December 21, 2006
Oregon Wave Energy Partners, LLC has filed a preliminary permit application for a proposed wave energy project that would be located 3-6 miles offshore in Lincoln County, Oregon. Comments and motions to intervene are due to FERC by February 18, 2007. ![]() Preliminary Permit application filed for Coos Bay Wave Park Project
By: John Seebach Thursday December 21, 2006
Oregon Wave Energy Partners, LLC has filed a preliminary permit application for a proposed wave energy project that would be located 2.5 miles offshore in Coos County, Oregon. Comments and motions to intervene are due to FERC by February 18, 2007. ![]() License amendment at Lake Dorothy Project
By: John Seebach Wednesday December 13, 2006
Project:
Lake Dorothy : P-12379
FERC has approved a license amendment for the Lake Dorothy project. The amendment authorizes the licensee to excavate a "starter tunnel" during construction that could later be used to further expand the project. ![]() Proposed license amendment on Carpenter-Remmel project
By: John Seebach Tuesday December 12, 2006
Project:
Carpenter-Remmel : P-271
Entergy Arkansas has applied for a license amendment that would allow the construction of a marina and boardwalk at the Carpenter-Remmel project. Comments are due on January 12, 2007. ![]() License amendment on Lower Raquette adds generation and environmental benefits
Project:
Lower Raquette River : P-2330
A license amendment for Erie Boulevard's Lower Raquette River project will increase the project's generating capacity by 50% (from 12 to 18 MW) while converting four dams from peaking generation into run-of-the-river mode, speeding up the license's fish protection and downstream fish passage measures by three years (from 2010 to 2007), and adding upstream eel passage at four dams. ![]() FERC amends license for Sturgeon Falls project
By: John Seebach Friday December 8, 2006
Project:
Sturgeon Falls : P-2720
FERC issued a license amendment which increased the authorized capacity of the Sturgeon Falls project to 6.4 MW. The licensee requested the amendment after rehabilitating several turbines that were damaged in December, 2005. ![]() |