NH

Errol Hydroelectric Project P-3133

General information

Waterway  Androscoggin River
Current status   Active license 
Type of facility Conventional Hydro
Type of permit FERC License

FERC information

FERC docket # P-3133
FERC project name Errol
Permit issued 8/24/83
Permit expiration 7/27/23

Ownership and operation

Owner Brookfield White Pine Hydro, LLC.
Owner type Wholesale Power Marketer
Year first online (conventional hydro) 1986
Transmission or distribution system owner Public Service Co of NH

Power and generating capacity

Number of units 1
Total capacity from hydraulic turbine-generator units within each plant 3.0 MW
Average annual net hydropower generation 16,827.8 MWH

Is there something you’d like to add or correct? Please let us know.