Turnagain Arm : P-13509

The applicant filed a successive preliminary permit application in January 2013. In July 2013, FERC noticed the application, which was approved through a new preliminary permit in February 2014. Proposed Conventional tidal energy project: 1,000-foot-wide concrete and...

Cook Inlet : P-12679

Update: ORCP surrendered the preliminary permit for this project in March 2013. Proposed tidal energy project. Two proposed developments: Fire Island & Anchorage. Fire Island to be constructed first. Fire Island: 4 turbine array initially; 39 kV transmission...

East Foreland : P-13821

The proponent of the project applied to renew the preliminary permit for the proposed East Foreland tidal project in March 2014 after the existing permit expired. FERC issued a successive preliminary permit on June 16, 2014 which is valid for two years. The proposed...