NY
Raymondville P-2330
General information | |
Waterway |
Raquette River |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river/Peaking |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-2330 |
FERC project name | Lower Raquette River |
Other projects with this FERC number | |
Permit issued | 2/8/02 |
Permit expiration | 12/27/33 |
Ownership and operation | |
Owner | Erie Boulevard Hydropower LP |
Owner type | Wholesale Power Marketer |
Year first online (conventional hydro) | 1928 |
Transmission or distribution system owner | Niagara Mohawk Power Corp. |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 2.0 MW |
Average annual net hydropower generation | 11,168.1 MWH |
This project on the Lower Raquette River project consists of four developments: Norwood, East Norfolk, Norfolk, and Raymondville.
Through a license amendment in December 2006, the project changed from peaking operation to run-of-river and also added upstream eel ladder at the dams.
Milestones
License Amendment Issued | 12-05-2006 |
FERC Certifies Tax Credits | 04-17-2009 |
Is there something you’d like to add or correct? Please let us know.
Related resources
News and updates
From Hydropower Reform Coalition11/19/2024
Monthly Newsletter: Exploring FERC-Exempt Hydro Projects: Small-Scale Hydropower with Big Impacts
From South Yuba River Citizens League9/25/2024
NID Withdraws Centennial Dam Proposal After SYRCL’s Decade-Long Opposition