NY
Rainbow Falls P-2835
General information | |
Waterway |
Ausable River |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-2835 |
FERC project name | Rainbow Falls |
Permit issued | 8/13/04 |
Permit expiration | 7/27/44 |
Ownership and operation | |
Owner | New York State Elec & Gas Corp |
Owner type | Investor-Owned Utility |
Year first online (conventional hydro) | 1926 |
Transmission or distribution system owner | New York State Elec & Gas Corp |
Power and generating capacity | |
Number of units | 2 |
Total capacity from hydraulic turbine-generator units within each plant | 2.6 MW |
Average annual net hydropower generation | 8,309.7 MWH |
Rainbow Falls Dam is the put-in for the Ausable Chasm whitewater run.
Is there something you’d like to add or correct? Please let us know.
News and updates
From Hydropower Reform Coalition11/19/2024
Monthly Newsletter: Exploring FERC-Exempt Hydro Projects: Small-Scale Hydropower with Big Impacts
From South Yuba River Citizens League9/25/2024
NID Withdraws Centennial Dam Proposal After SYRCL’s Decade-Long Opposition