CA
Papazian (Fairfield) P-3116
General information | |
Waterway |
Legrand and Fairfield Canals |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Canal/Conduit |
Type of permit | FERC Exemption |
FERC information | |
FERC docket # | P-3116 |
FERC project name | Fairfield |
Permit issued | 10/25/80 |
Ownership and operation | |
Owner | Merced Irrigation District |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 1982 |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 0.9 MW |
Average annual net hydropower generation | 1,966.0 MWH |