MD
Brighton P-3633
General information | |
Waterway |
Patuxent River |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Peaking |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-3633 |
FERC project name | Brighton |
Permit issued | 9/16/84 |
Permit expiration | 8/27/24 |
Ownership and operation | |
Owner | KC Brighton LLC |
Owner type | Private Non-utility |
Year first online (conventional hydro) | 1986 |
Power and generating capacity | |
Number of units | 2 |
Total capacity from hydraulic turbine-generator units within each plant | 0.4 MW |
Average annual net hydropower generation | 2,100.0 MWH |