CO

Miller Creek Ditch Hydropower Project CD16-8

General information

Waterway  Miller Creek Ditch
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Canal/Conduit
Type of permit FERC Qualifying Conduit

FERC information

FERC docket # CD16-8
Permit issued 4/23/16

Ownership and operation

Owner White River Electric Association
Owner type Cooperative
Year first online (conventional hydro) 2017

Power and generating capacity

Number of units 1
Total capacity from hydraulic turbine-generator units within each plant 0.2 MW
Average annual net hydropower generation 504.0 MWH

Is there something you’d like to add or correct? Please let us know.

News and updates

From California Sportfishing Protection Alliance11/24/2024

FERC Holds PG&E Accountable for 2023 Butte Canal Failure

See all news and updates