UT

Silver Creek Hydro Energy Recovery Facility CD17-7

General information

Waterway  Signal Hill Water Treatment Plant
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Canal/Conduit
Type of permit FERC Qualifying Conduit

FERC information

FERC docket # CD17-7
Permit issued 2/22/17

Ownership and operation

Owner Mountain Regional Water Special Service District
Owner type Political subdivision
Year first online (conventional hydro) 2018

Power and generating capacity

Number of units 2
Total capacity from hydraulic turbine-generator units within each plant 0.2 MW
Average annual net hydropower generation 1,000.0 MWH

Is there something you’d like to add or correct? Please let us know.

News and updates

From California Sportfishing Protection Alliance11/24/2024

FERC Holds PG&E Accountable for 2023 Butte Canal Failure

See all news and updates