CA
Azusa P-1250
General information | |
Waterway |
San Gabriel River |
Current status | Active license  |
Type of facility | Conventional Hydro |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-1250 |
FERC project name | Azusa |
Permit issued | 12/31/88 |
Permit expiration | 12/27/18 |
Ownership and operation | |
Owner | City of Pasadena |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 1949 |
Transmission or distribution system owner | Southern California Edison Co |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 3.0 MW |
Average annual net hydropower generation | 1,785.4 MWH |
Is there something you’d like to add or correct? Please let us know.
News and updates
From California Sportfishing Protection Alliance11/24/2024
From Hydropower Reform Coalition11/19/2024
Monthly Newsletter: Exploring FERC-Exempt Hydro Projects: Small-Scale Hydropower with Big Impacts