ME

Bar Mills : P-2194

[ Active ]

Waterway: Saco R

Authorized capacity: 4 mW

License issued: 8/26/2008
License expires: 7/31/2048

Licensee: Brookfield White Pine Hydro, LLC.

The Bar Mills Project consists of a 364-foot-long, 7-foot-high concrete gravity dam that impounds a 263-acre, 5.3-mile-long reservoir. The powerhouse contains two 2.0-MW generating units that discharge water into a 200-foot-long tailrace.

Project power is transmitted through a 30-foot-long, 34/2.4 kilovolt (kV) transmission line connected to the regional grid.

Milestones

New License Issued 08-26-2008