VT
Barton Village P-7725
General information | |
Waterway | Clyde River |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-7725 |
Permit issued | 6/4/2004 |
Permit expires | 9/27/2043 |
Ownership and operation | |
Owner | Barton Village, Inc |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 1931 |
Transmission or distribution system owner | Barton Village, Inc |
Power and generating capacity | |
Number of units | 2 |
Total capacity from hydraulic turbine-generator units within each plant | 1.4 mW |
Average annual net hydropower generation | 2,406.4 mWH |
News and updates
From American Whitewater1/21/2021
From American Whitewater1/19/2021