General information

Waterway  San Joaquin River
Current status   Active license 
Type of facility Conventional Hydro
Type of permit FERC License

FERC information

FERC docket # P-120
FERC project name Big Creek No 3
Permit issued 9/2/77
Permit expiration 2/24/09

Ownership and operation

Owner Southern California Edison Co
Owner type Investor-Owned Utility
Year first online (conventional hydro) 1923
Transmission or distribution system owner Southern California Edison Co

Power and generating capacity

Number of units 5
Total capacity from hydraulic turbine-generator units within each plant 174.5 MW
Average annual net hydropower generation 664,863.4 MWH