AK
Blue Lake P-2230
General information | |
Waterway |
Sawmill Creek |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Peaking |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-2230 |
FERC project name | Blue Lake |
Other projects with this FERC number | |
Permit issued | 7/5/07 |
Permit expiration | 3/27/38 |
Ownership and operation | |
Owner | Sitka City & Borough of |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 2014 |
Transmission or distribution system owner | City & Borough of Sitka - (AK) |
Power and generating capacity | |
Number of units | 3 |
Total capacity from hydraulic turbine-generator units within each plant | 15.9 MW |
Average annual net hydropower generation | 50,141.4 MWH |
This project, located on Sawmill Creek in the Borough of Sitka, Alaska, occupies 1,628.1 acres of federal lands administered by the U.S. Forest Service.
The Blue Lake Project is operated in conjunction with the Green Lake Project No. 2818. The Blue Lake Project is operated to meet daily base loads and the Green Lake Project is operated to meet daily peak loads. Both project reservoirs are drawn down during winter when inflow to the reservoirs decreases and the demand for electricity increases.
Is there something you’d like to add or correct? Please let us know.
News and updates
From South Yuba River Citizens League9/5/2023
The Possible Impacts of the EPA Redefining “Waters of the United States” on the Yuba Watershed
From Idaho Rivers United9/1/2023