Burnham P-11472
General information | |
Waterway | Sebasticook River |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river/Peaking |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-11472 |
FERC project name | Burnham |
Permit issued | 4/2/2004 |
Permit expires | 10/27/2036 |
Ownership and operation | |
Owner | KEI (Maine) Power Management (III) LLC |
Owner type | Private Non-utility |
Year first online (conventional hydro) | 1986 |
Transmission or distribution system owner | Central Maine Power Co |
Power and generating capacity | |
Number of units | 3 |
Total capacity from hydraulic turbine-generator units within each plant | 1.1 mW |
Average annual net hydropower generation | 4,455.1 mWH |