ME

Burnham P-11472

General information

Waterway  Sebasticook River
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Run-of-river/Peaking
Type of permit FERC License

FERC information

FERC docket # P-11472
FERC project name Burnham
Permit issued 4/2/04
Permit expiration 10/27/36

Ownership and operation

Owner KEI (Maine) Power Management (III) LLC
Owner type Private Non-utility
Year first online (conventional hydro) 1986
Transmission or distribution system owner Central Maine Power Co

Power and generating capacity

Number of units 3
Total capacity from hydraulic turbine-generator units within each plant 1.1 MW
Average annual net hydropower generation 4,455.1 MWH

Is there something you’d like to add or correct? Please let us know.

Related resources

News and updates

From California Sportfishing Protection Alliance4/28/2025

PG&E proposes “rapid removal” plan for Cape Horn and Scott dams on the Eel River 

From California Sportfishing Protection Alliance2/25/2025

State Water Board Takes Action to Protect Klamath River Salmon and Steelhead

See all news and updates