CA
CPUD Pipeline P-7283
General information | |
Waterway |
Jeff Davis Reservoir |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Canal/Conduit |
Type of permit | FERC Exemption |
FERC information | |
FERC docket # | P-7283 |
FERC project name | CPUD Pipeline |
Permit issued | 10/21/83 |
Ownership and operation | |
Owner | Calaveras Public Utility District |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 1984 |
Power and generating capacity | |
Number of units | 3 |
Total capacity from hydraulic turbine-generator units within each plant | 0.3 MW |