General information

Waterway  Escanaba River
Current status   Active 
Type of facility Conventional Hydro
Mode of hydropower generation Run-of-river
Type of permit FERC License

FERC information

FERC docket # P-2506
FERC project name Escanaba
Other projects with this FERC number
Permit issued 7/8/95
Permit expiration 6/26/35

Ownership and operation

Owner Upper Peninsula Power Co
Owner type Investor-Owned Utility
Year first online (conventional hydro) 1926
Transmission or distribution system owner City of Escanaba

Power and generating capacity

Number of units 1
Total capacity from hydraulic turbine-generator units within each plant 10.0 MW
Average annual net hydropower generation 20,305.0 MWH