Essex Junction 19 P-2513

General information

Waterway  Winooski River
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Run-of-river
Type of permit FERC License

FERC information

FERC docket # P-2513
FERC project name Essex No 19
Permit issued 3/25/95
Permit expiration 2/24/25

Ownership and operation

Owner Green Mountain Power Corp
Owner type Investor-Owned Utility
Year first online (conventional hydro) 1917
Transmission or distribution system owner Green Mountain Power Corp

Power and generating capacity

Number of units 5
Total capacity from hydraulic turbine-generator units within each plant 8.0 MW
Average annual net hydropower generation 37,758.6 MWH