CO

Georgetown P-2187

General information

Waterway  South Clear Creek
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Peaking
Type of permit FERC License

FERC information

FERC docket # P-2187
FERC project name Georgetown
Permit issued 2/23/96
Permit expiration 5/26/36

Ownership and operation

Owner Public Service Co of Colorado
Owner type Investor-Owned Utility
Year first online (conventional hydro) 1906
Transmission or distribution system owner Public Service Co of Colorado

Power and generating capacity

Number of units 2
Total capacity from hydraulic turbine-generator units within each plant 1.2 MW
Average annual net hydropower generation 3,959.5 MWH

Is there something you’d like to add or correct? Please let us know.

News and updates

From California Sportfishing Protection Alliance11/24/2024

FERC Holds PG&E Accountable for 2023 Butte Canal Failure

See all news and updates