NY
High Falls P-2951
General information | |
Waterway |
Rondout Creek |
Current status | Active license  |
Type of facility | Conventional Hydro |
Type of permit | FERC Exemption |
FERC information | |
FERC docket # | P-2951 |
FERC project name | High Falls |
Permit issued | 4/24/83 |
Ownership and operation | |
Owner | Central Hudson Gas & Elec Corp |
Owner type | Investor-Owned Utility |
Year first online (conventional hydro) | 1986 |
Transmission or distribution system owner | Central Hudson Gas & Elec Corp |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 3.2 MW |
Average annual net hydropower generation | 5,312.2 MWH |