ID
Kirby P-11541
General information | |
Waterway | Middle Fork Boise River |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-11541 |
FERC project name | Atlanta Power Station |
Permit issued | 5/4/2002 |
Permit expires | 4/26/2032 |
Ownership and operation | |
Owner | Atlanta Power Co Inc |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 1963 |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 0.2 mW |
Average annual net hydropower generation | 1,314.0 mWH |