ME
McKay P-2572
General information | |
Waterway |
West Branch Penobscot River |
Current status | Active license  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Peaking |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-2572 |
FERC project name | Ripogenus |
Permit issued | 10/17/96 |
Permit expiration | 9/26/26 |
Ownership and operation | |
Owner | Great Lakes Hydro America LLC |
Owner type | Wholesale Power Marketer |
Year first online (conventional hydro) | 1917 |
Transmission or distribution system owner | Emera Maine |
Power and generating capacity | |
Number of units | 3 |
Total capacity from hydraulic turbine-generator units within each plant | 37.6 MW |
Average annual net hydropower generation | 197,413.5 MWH |
Please see additional project information in this 2020 factsheet created by Kaitlyn Raffier, Sharon Klein, and Emma Fox as part of the Future of Dams collaborative research project between the University of Maine, University of New Hampshire, and others.
Is there something you’d like to add or correct? Please let us know.
News and updates
From California Sportfishing Protection Alliance11/24/2024
From Hydropower Reform Coalition11/19/2024
Monthly Newsletter: Exploring FERC-Exempt Hydro Projects: Small-Scale Hydropower with Big Impacts