ID

Mile 28 Water Power Project P-10552

General information

Waterway  Milner-Gooding Canal
Current status  Active 
Type of facility Conventional Hydro
Mode of hydropower generation Canal/Conduit
Type of permit FERC License

FERC information

FERC docket # P-10552
Permit issued 8/7/1992
Permit expires 7/27/2042

Ownership and operation

Owner Mi-28 Water Power Project LLC
Owner type Private Non-utility
Year first online (conventional hydro) 1994
Transmission or distribution system owner Idaho Power Co

Power and generating capacity

Number of units 2
Total capacity from hydraulic turbine-generator units within each plant 1.4 mW
Average annual net hydropower generation 4,226.4 mWH

From our Resource Library