Mottville : P-401

[ Active ]

Waterway: St Joseph R

Authorized capacity: 1.68 mW

License issued: 4/17/2003
License expires: 9/18/2033

Licensee: Indiana Michigan Power Co

Milestones

FERC decision on license application 12-01-2007
FERC submits final EIS 10-01-2007
FERC submits draft EIS 06-01-2007
Deadline to file comments regarding recommendations, terms and conditions, and prescriptions. 03-14-2007
Deadline to file motion to intervene. 01-28-2007
FERC submits Ready for Environmental Analysis 11-01-2006
FERC will accept license application 08-01-2006
Additional information requests to FERC 05-30-2006
SCE submits license application and draft EA to FERC 12-07-2005
SCE files Notice of Intent to seek a new license 10-04-2005