ID

Pancheri P-5637

General information

Waterway  Telford Pipeline
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Canal/Conduit
Type of permit FERC Exemption

FERC information

FERC docket # P-5637
FERC project name Pancheri
Permit issued 3/10/82

Ownership and operation

Owner Pancheri, Inc.
Owner type Private Non-utility
Year first online (conventional hydro) 1983

Power and generating capacity

Number of units 1
Total capacity from hydraulic turbine-generator units within each plant 0.2 MW
Average annual net hydropower generation 1,048.0 MWH

Is there something you’d like to add or correct? Please let us know.