CO

Pandora Water System Project CD14-5

General information

Waterway  Conduit/Canal
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Canal/Conduit
Type of permit FERC Qualifying Conduit

FERC information

FERC docket # CD14-5
Permit issued 1/2/14

Ownership and operation

Owner Town of Telluride
Owner type Publicly Owned Utility
Year first online (conventional hydro) 2014

Power and generating capacity

Number of units 1
Total capacity from hydraulic turbine-generator units within each plant 0.3 MW
Average annual net hydropower generation 2,135.0 MWH

Is there something you’d like to add or correct? Please let us know.