OK

Pensacola P-1494

General information

Waterway  Neosho River
Current status   Active license 
Type of facility Conventional Hydro
Mode of hydropower generation Peaking
Type of permit FERC License

FERC information

FERC docket # P-1494
FERC project name Pensacola
Permit issued 4/19/92
Permit expiration 3/27/22

Ownership and operation

Owner Grand River Dam Authority
Owner type State
Year first online (conventional hydro) 1940
Transmission or distribution system owner Grand River Dam Authority

Power and generating capacity

Number of units 7
Total capacity from hydraulic turbine-generator units within each plant 130.1 MW
Average annual net hydropower generation 415,151.5 MWH