CA
Perdue Water Treatment Plant Hydroelectric Project CD15-30
General information | |
Waterway |
Conduit/Canal |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Canal/Conduit |
Type of permit | FERC Qualifying Conduit |
FERC information | |
FERC docket # | CD15-30 |
Permit issued | 9/12/15 |
Ownership and operation | |
Owner | Sweetwater Authority |
Owner type | Publicly Owned Utility |
Year first online (conventional hydro) | 2017 |
Power and generating capacity | |
Number of units | 2 |
Total capacity from hydraulic turbine-generator units within each plant | 0.7 mW |
Average annual net hydropower generation | 3,784.0 mWH |