CT

Stevenson P-2576

General information

Waterway  Housatonic River
Current status  Active 
Type of facility Conventional Hydro
Mode of hydropower generation Peaking
Type of permit FERC License

FERC information

FERC docket # P-2576
Permit issued 6/18/2004
Permit expires 5/27/2044

Ownership and operation

Owner FirstLight Power Resources Services LLC
Owner type Wholesale Power Marketer
Year first online (conventional hydro) 1919
Transmission or distribution system owner Connecticut Light & Power Co

Power and generating capacity

Number of units 4
Total capacity from hydraulic turbine-generator units within each plant 30.5 mW
Average annual net hydropower generation 98,541.7 mWH