WA
Twin Falls Hydro P-4885
General information | |
Waterway | South Fork Snoqualmie River |
Current status | Active  |
Type of facility | Conventional Hydro |
Mode of hydropower generation | Run-of-river |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-4885 |
Permit issued | 5/1/1985 |
Permit expires | 4/26/2035 |
Ownership and operation | |
Owner | Twin Falls Hydro Associates LP |
Owner type | Private Non-utility |
Year first online (conventional hydro) | 1989 |
Transmission or distribution system owner | Puget Sound Energy Inc |
Power and generating capacity | |
Number of units | 2 |
Total capacity from hydraulic turbine-generator units within each plant | 24.0 mW |
Average annual net hydropower generation | 69,807.2 mWH |
News and updates
From Trout Unlimited2/26/2021
From California Trout2/26/2021