MA
Willow Mill P-2985
General information | |
Waterway | Housatonic River |
Current status | Active  |
Type of facility | Conventional Hydro |
Type of permit | FERC License |
FERC information | |
FERC docket # | P-2985 |
Permit issued | 4/26/1981 |
Permit expires | 4/26/2011 |
Ownership and operation | |
Owner | MeadWestvaco Corporation |
Owner type | Industrial |
Year first online (conventional hydro) | 1930 |
Power and generating capacity | |
Number of units | 1 |
Total capacity from hydraulic turbine-generator units within each plant | 0.1 mW |
While undergoing relicensing, the license owner for this project surrendered its license citing economic reasons. FERC approved the surrender in 2012.
The project consists of a masonry gravity dam (14 ft high and 150 ft wide) and an 11-acre impoundment.
The power generated from this project is used at the Willow Mill.
Milestones
Minor Licence Application Filed | 04-29-2009 |
News and updates
From California Sportfishing Protection Alliance1/23/2021
CSPA Defends Cold Water for North Fork Feather River & Lake Almanor
From American Rivers1/22/2021