Bangor Hydro-Electric Company v. FERC

Court cases Published   1/1/1996

78 F.3d 659 (D.C. Dist. 1996)

Issue. Was FERC or the prescriptive agency the proper party in a § 18 fishway dispute?
Holding. A fishway prescription included in a FERC order may only be challenged in a petition identifying FERC as the respondent because FERC is the real governmental
party in interest.

HRC or member-contributed

Submitted to this collection by:

Hydropower Reform Coalition