California v. FERC

From:

Hydropower Reform Coalition
Court CasesPublished   1/1/1990

495 U.S. 490 (1990)

Issue. Does FERC have exclusive jurisdiction to determine the minimum flow schedule for a hydropower project?
Holding. FERC has exclusive jurisdiction to set the flow schedule for a hydropower project to the extent that the schedule provides for non-proprietary uses of water.