Reservoir Drawdown Begins for Klamath River Dam Removal

Published 1/12/2024  |  California Trout

Iron Gate Dam by Ren Brownell / KRRC

The next big step in Klamath River dam removal is here: reservoir drawdown. On January 11, 2024, initiated the drawdown process by opening the low-level outlet tunnel in the Iron Gate Dam. This is an exciting milestone towards dam removal, and we are thrilled to share the news with you!

Update from the Klamath River Renewal Corporation:

“Drawdown refers to the slow draining of the water in the reservoirs, which will be lowered in a controlled manner through tunnels located at the base of the dams. Drawdown of the JC Boyle and Copco Reservoirs will begin later this month, and all reservoirs are expected to be drained by the end of February.

“Witnessing the beginning of drawdown at Iron Gate dam was both celebration of an important moment in the story of Klamath dam removal, and a source of pride for the exceptional work done by so many people to arrive at this day.” Said Mark Bransom, CEO of KRRC.

Communities downstream of the dams will start to see changes in the river in the coming days, as sediment that has accumulated behind the dams is evacuated downstream. There is an estimated 17-20 million cubic yards of sediment behind Iron Gate, JC Boyle, and Copco No. 1, the three remaining Klamath dams slated for removal. During the drawdown process 5-7 million cubic yards is expected to go downstream during the initial phase of drawdown in January and February. Extensive testing done by the U.S. Environmental Protection Agency and KRRC consultants has determined the sediment to be non-toxic, mostly consisting of dead algae, gravels, and fine clay particulates.

“Iron Gate’s drawdown strategy is different than what people may have seen in the past with other dam removals,” noted Bransom. “There was no blast at this dam, instead we had the opportunity to use existing infrastructure, which allows us to precisely control the volume of water going down river, limiting downstream impacts.”

The initial drawdown period was carefully selected KRRC’s Aquatic Resources Working Group, which is comprised of Tribes, and state and federal agencies. January and February are the ideal months for this process, as there are the fewest threated and endangered species in the mainstem, and winter flows will assist with sediment evacuation.

While the initial phase of drawdown is expected to be completed sometime in February, because the reservoirs will be drained so slowly, they may refill a bit with spring run-off, and then need to drain again. Water quality is expected to improve in March, after the initial phase of drawdown is complete, but it will likely take up to 24 months for water to return to usual clarity, following the successful establishment of vegetation in the former reservoir footprint areas. Work on the deconstruction of the dams is expected to commence sometime in May or June of 2024 depending on the weather, and be complete by Fall, 2024.”

 

The post Reservoir Drawdown Begins for Klamath River Dam Removal appeared first on California Trout.

Email newsletter