Alabama Rivers Alliance v. FERC

Court cases

325 F.3d 290 (D.C. Cir. 2003)

Issue. Was the installation and operation of the three new turbine generators at the project an activity which may result in any discharge for purposes of § 401(a)(1) of the CWA?
Holding. The licensee must obtain a new or amended water quality certification under CWA section 401(a)(1) if the replacement of the generators will alter (either increase or decrease) the quantity of flow discharge.

  HRC or member-contributed resource

Contributed by:

Hydropower Reform Coalition

 

View PDF

Related resource

Court cases

LaFlamme v. FERC

Issue 1. When does FERC have to prepare an Environmental Impact Statement (EIS) for a project?