Alabama Rivers Alliance v. FERC

HRC or member-contributed

Submitted to this collection by:

Hydropower Reform Coalition

 

  View PDF

Court cases Published   2/20/2020

325 F.3d 290 (D.C. Cir. 2003)

Issue. Was the installation and operation of the three new turbine generators at the project an activity which may result in any discharge for purposes of § 401(a)(1) of the CWA?
Holding. The licensee must obtain a new or amended water quality certification under CWA section 401(a)(1) if the replacement of the generators will alter (either increase or decrease) the quantity of flow discharge.