Boardman River Projects, Boardman River, Michigan

HRC or member-contributed

From:

Hydropower Reform Coalition, Michigan Hydro Relicensing Coalition

 

  View PDF

Decommissioning and removalLicense SummariesMidwestPublished   1/1/2009

The licensee of the project decided that the project was not economically feasible for relicensing. Through a settlement of which HRC/MHRC was a part, the licensee decided to decommission the project, opening the door for dam removal. For relicensing, Federal Energy Regulatory Commission (FERC) wanted the licensee to install emergency spillways at Brown Bridge dam.

The three dams were removed between 2012 and 2019. The whole story of the Boardman River restoration is at http://theboardman.org.

More from our resource librarySee all

Decommissioning and removal › Recommended Reading   12/1/2011

Restore: A Special Publication by the Hydropower Reform Coalition